Mathematics UTME / JAMB 2005 Number and Numeration
The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many men are required to do the work in 4 days?
A
20
B
35
C
45
D
60